![]() Text and photographs copyright of Jim Shead. |
|
Spring 1826 | Between 10th April and 1st May he gave evidence to a formal enquiry into the Bill to authorise the cut. He proposed a doudle lock at Munford bridge with gates pointing both ways and the further use of steam tugs. | |
Spring 1826 | Between 10 April and 1 May he, and five other leading civil engineers, gave evidence to parliament on the Bill to build the cut. | |
April 1826 | Between 10 April and 1 May he, and five other leading civil engineers, gave evidence to parliament on the Bill to build the cut. | |
April 1826 | Between 10 April and 1 May he, and five other leading civil engineers, gave evidence to parliament on the Bill to build the cut. | |
April 1826 | Between 10 April and 1 May he, and five other leading civil engineers, gave evidence to parliament on the Bill to build the cut. | |
April 1826 | Between 10 April and 1 May he, and five other leading civil engineers, gave evidence to parliament on the Bill to build the cut. | |
1827 | Promoted by Act as the Norwich and Lowestoft Navigation. | |
1832 | He completed his work directing the building of the cut. | |
1833 | Was opened in 1833 as the Norwich and Lowestoft Navigation. | |
Description: Various proposals for a coast to coast waterway that was never authorised or built.
History: The propasals started in 1794 and were still being supported in 1810.
1794 | He did the quick preliminary survey for the scheme before William Chapman and William Jessop did the detailed survey. | |
Late 1794 | He was associated with William Chapman in his survey of the route and plans for the canal. | |
5 January 1795 | He made a preliminary report on the canal. | |
June 1795 | He publised a pamphlet proposing a Stella to Hexham canal on the soth side of the Tyne and estimated a cost of £35,709 for 18 miles of canal with 12 locks. | |
Summer 1795 | Between 26 June and 10 August he issued three parts of a detailed study on a proposed route from the north side of the Tyne at Newcastle, to Hexham and Haydon Bridge, through the Tyne and Irthling valleys to Carlisle and Maryport. | |
26 October 1795 | He agreed with William Chapman's line on the north side of the Tyne and thought that an estimate of £3,737 per mile was not high. He and Chapman jointly signed the estimate of £355,067 for the 95 mile canal. | |
1796 | He rejected Ralph Dodd's plans and proposed a different Stella to Hexham line 44 feet wide at the surface and 6 feet deep taking craft between 50 and 60 tons, but not exsisting keels. This 17 mile, 18 lock route was estimated at almost £90,000 to bring a revenue of £23,460 and a net yield of £17,595. | |
After 1796 | Around this time he produced another report for the extension of the canal to Haydon Bridge and rported on the north side line with a detailed estimate and attacked Ralph Dodd, William Chapman and especially William Jessop. | |
Early 1797 | Having looked at John Sutcliffe's plans he approved the line although it "is a rugged one; I never before saw a good line like it; yet so far as I can discover, I believe it is the best the country affords: It is certainly practicable, and I have no doubt but that a good and useful canal may be made (with some variation) upon it; but it will be exceedingly expensive: I am, however, told the trade that will come upon this canal will fully answer that expence, even were it twice as much.". | |
Summer 1824 | Wrote a pamphlet explaining that his 1796 route for the canal could be used as the line for a railway. |
Description: A proposal for a canal from Pixton on the Cromford Canal to the Chesterfield Canal and onwards from Hillmarsh on the Chesrterfield Canal to Rotherham, where it joined the River Don.
History: A public meeting was held on 26 October 1810 and John Rennie surveyed the route.It was supported by the Cromford Canal Company and in 1811 the Nottingham Canal Company recommended that their shareholders give it support. It was still being discussed in September 1814 but was never authorised or built.
Autumn 1810 | He surveyed the route for the canal which he considered favourable. |
Description: Runs 91 miles from Northampton, where it joins the Northampton Branch of the Grand Union Canal, to the Wash. The lower 26 miles (from Dog-in-a-Doublet Lock) are tidal.
History: Promoted by Acts of 1713 (no work done), 1724, 1754, 1756, 1794, 1827 and 1829. Navigation from Thrapston to Peterborough promoted by the 1724 Act and navigation from Thrapston to Northampton promoted by the Act 1756. Navigation from Northampton to Peterborough was opened in 1761.
See Priestley's Navigable Rivers and Canals for more information.
1649 | He completed works on the outfall and improved Morton Leam. | |
1713 | Promoted by Act but no work done. | |
1721 | Work started on the new cut he proposed to straighten the river between Peterbough and Wisbech. Although nearly all the work was done a change of mind by the Wisbech corporation delayed its openning until 1773. | |
1724 | Navigation from Thrapston to Peterborough promoted by Act. | |
1753 | He surveyed the river from Thrapston to Northampton. | |
After 1753 | He proposed a plan for making the river navigable from Thrapston to Northampton for 13,000 guineas. | |
1754 | Promoted by Act. | |
1754 | Around this time he put proposals to the Western Division commissioners for making their part of the river navigable. | |
1756 | Navigation from Thrapston to Northampton promoted by Act. | |
Early 1758 | Put in plans for improvements to the Western Division of the river but later dissented from these proposals and the terms required for the work. | |
March 1758 | He put in an estimate for improving the navigation between Thrapston and Northampton. His plans were rejected in favour of those from a Mr Case who later withdrew his proposals. Smith then submitted new plans and an estimate of £14,070 4s 2½d that was accepted. | |
Spring 1758 | He was asked examine the propsals of John Smith junior and Mr Wyman for making the western division of the river navigable and found that both schemes were sound. | |
Spring 1758 | He put forward a proposal for making the river navigable from Thrapston to Northampton. His plan was approved by Thomas Yeoman but he withdrew in favour of a plan by John Smith junior "on account of Mr Smith's cheaper proposals, his Integrity and superior Experience in such affairs". | |
22 June 1758 | The contract was signed for his river improvements that included 20 pound-locks 10 feet 6 inches wide and 100 feet long. | |
1759 | He reported that the navigation between Wansford and Waternewton was very bad in places and that the commissioners seem to have had little or no authority over the proprietors, who had sole use of the tolls for themselves. | |
1759 | The navigation reached Wellingborough where he built wharves. | |
1761 | Navigation from Northampton to Peterborough opened. | |
Late 1761 | Around this time he surveyed the newly opened navigation and gave it a favourable report. | |
7 August 1761 | His navigation works to Northampton were completed. | |
1768 | He reported on the outfall and the drainage of the North Level and estimating a cost of £20,695 for his proposed solution. | |
1769 | He agreed that no permanent solution to flooding on the river could be found until the obstructions at Wisbech were removed.He also recommended a navigable sluice above Guyhirne and a side cut through Wisbech. | |
1771 | He reported on the problems with the river outfall. | |
1771 | He ageed that no permanent solution to flooding on the river could be found until the obstructions at Wisbech were removed. | |
1794 | Promoted by Act. | |
1801 | The Deeping Fen Act was passed based on two reports, one of which he prepared with John Rennie. | |
1801 | The Deeping Fen Act was passed based on two reports, one of which he prepared with William Jessop. | |
1802 | He, together with Charles Handley, was retained by the Western Division commisioners to prove that sufficient water supply could be found for the Grand Junction Canal Company to build a canal link to Northampton. | |
1802 | The commissioners called on his services to prove that there was a sufficient water supply to enable the Northampton Arm to be built to connect the river to the Grand Junction Canal. | |
1814 | He reported to the Bedford Level Corporation on a Nene outfall cut which included the recommendation for a 3½: mile staight cutby-passing Wisbech on the north side. The passage to Wisbech was to be controlled by flood gates and a lock. | |
1822 | He and Sir John Rennie were asked for revised plans for the river outfall and its passage through Wisbech. | |
1822 | He and Thomas Telford were asked for revised plans for the river outfall and its passage through Wisbech. | |
1825 | Appointed surveyor of the river and inspected the Eastern Division locks in a boat, which he had bought for £36. | |
1825 | The western commissioners asked him to survey the river and he found the locks badly constructed and in bad condition. He recommended that a surveyor be appointed "that understands something of the management of canals", the full-time employment of bricklayers and carpenters, the setting up of a repair yard and the booking of all materials. | |
1827 | Promoted by Act. | |
1827 | He and Sir John Rennie are appointed as engineers for the Wisbech cut. | |
1827 | He and Thomas Telford are appointed as engineers for the Wisbech cut. | |
1827 | Resigned as surveyor. | |
1827 | Appointed surveyor for the river, following the resignation of the former surveyor, Joseph Aris. | |
After 1827 | He had the 1818 order banning Grand Junction Canal boats from the river rescinded. | |
1829 | Promoted by Act. | |
1831 | He completed his work of overseeing the stoning of the banks for works under the 1827 Act. He is refered to as John Pear on page 213 of The Canals of Eastern England but as Thomas in the index entry. | |
1831 | He was resident engineer for the Wisbech cut that had now been completed two years earlier than the Act required. The Nene Outfall commisioners especially praised him, John Pear who superintended the stoning of the banks and the contractors Joliffe & Banks. | |
28 February 1834 | He and Sir John Rennie certify the completion of the new outfall cut, which cost £200,716. | |
28 February 1834 | He and Thomas Telford certify the completion of the new outfall cut, which cost £200,716. | |
1836 | He proposed the removal of the stone bridge at Wisbech and the adjoining houses so that the sectional area of the river could be doubled. He also recommended impovements to permit vessels with a 7 foot draught to reach Peterborough and a back cut in Wisbech to avoid the S bend through the town. He ageed that no permanent solution to flooding on the river could be found until the obstructions at Wisbech were removed. | |
1840 | Represented the Nene Commissioners at a meeting to consider John Rennie's report on improvements to the lower river. | |
1847 | He ageed that no permanent solution to flooding on the river could be found until the obstructions at Wisbech were removed. | |
1850 | His iron bridge at Sutton was opened about 100 feet south of the site of the original oak bridge with a moveable iron centre span that it repalced. | |
1851 | About this date he surveyed the river made a report to the commiittee on Nene drainage. | |
1852 | He is appointed engineer and began a major dredging and embanking project costing an estimated £124,800. | |
1855 | Around this time he was appointed engineer and built two dams across the river above Wisbech, one at Waldersea and the other at Guyhirne. He also made a submerged weir with a pair of check-gates below the new bridge at Wisbech. This was done as a temporary measure to guard against floods and to reduce bank errosion but the works caused increased silting and much controversy. | |
After 1859 | Following an accident involving a gang of lighters he recommended the removal of the restriction to the river flow, or throttle, at Wisbech. | |
1909 | As engineer of the Nene third district he gave evidence to the Royal Commission on Canals and Waterways on the poor state of the Wisbech Canal and River Nene. | |
1916 | The River Nene. By P Bonthron. First published. | |
After 1930 | Was responsible for rebuilding locks and sluices on the river and building a new lock and weir at Dog-in-a-Doublet. | |
1967 | A Summer on the Nene by D J Watkins-Pitchford, Published by Kaye & Ward - Account of a summer voyage illustrated by the woodcuts of the author. | |
1971 | IWA National Rally at Northampton. | |
1976 | IWA National Festival at Peterborough. | |
1991 | Along the Nene by H J K Jenkins, Published by Cambridgeshire Books. | |
1993 | IWA National Festival at Peterborough. | |
1997 | The River Nene From Source to Sea by David Phillips, Published by Past & Present - A well illustrated guide to the river and the places along its banks. | |
Description: A canal proposed in 1810 but never authorised or built.
1810 | He surveyed the line for the canal. |
Description: A 2.5 mile underground level navigation in a lead mine at Alston, Cumberland.
History: Work started in 1776 to a plan by John Smeaton, John Gilbert recommended widening in 1777, completed by 1810.
1775 | He and Richard Walton, his fellow Receiver for the mining rights to Alston Moor, prepared a report for the Commissioners of Greenwich Hostipal who were the owners of the land. They proposed a 3 mile drainage tunnel intersecting a number of lead ore veins which would have been uneconomical to work without drainage. | |
1776 | Work started in 1776 to a plan by John Smeaton. | |
1777 | John Gilbert recommended widening. | |
1810 | Completed by 1810. | |
Description: Originally a 14.75 mile broad canal from Langley Mill, on the Erewash Canal, to Nottingham, on the Trent Navigation. Abandoned and mostly un-navigable.
History: Promoted under an Act of 1792, opened in 1796, abandoned in 1937 except for the section from the Trent to Beeston Cut which is now part of the River Trent Navigation.
See Priestley's Navigable Rivers and Canals for more information.
Late 1790 | He was asked to survey the canal and a branch from Lenton to the Trent at Beeston. He started his survey and found that the line suggested by Lord Middleton was impracticable because it needed tunnelling and deep cuttings but then he fell ill and suggested that James Green should complete the survey. | |
June 1791 | He has been ill for six months and the committee now agree that James Green should do the survey under Jessop's supervision. He says "I am still confined but hope next week to be able to get out with my head wrapped up". | |
June 1791 | Surveyed a line for the canal under William Jessop's supervision. | |
September 1791 | He submitted his estimate for the canal. | |
1792 | Promoted under an Act. | |
1792 | He is appointed engineer at 3 guineas a day. | |
1792 | Was appointed engineer at 300 guineas a year under William Jessop. | |
October 1794 | The committee criticise him for not paying enough attention to the canal. | |
1796 | Opened. | |
1937 | Abandoned in 1937 except for the section from the Trent to Beeston Cut which is now part of the River Trent Navigation. | |
Description: Was a 4.5 mile, 13 lock, broad canal from Shipley Wharf, near Ilkeston, Derbyshire, to White House, Staunton, where in joined the Erewash Canal.
History: Authorised by an Act of 1793, opened about 1796. No traffic after 1949 and much of the canal filled in now.
See Priestley's Navigable Rivers and Canals for more information.
1791 | He surveyed the line of this proposed branch to be built by the Erewash Canal company. | |
1793 | Authorised by an Act. | |
1793 | He was paid for the preliminary survey of the canal. | |
1793 | He was appointed engineer. | |
1796 | Opened about 1796. | |
1949 | No traffic after 1949 and much of the canal filled in now. | |
Description: Runs 13 mile canal runs from Glyn Neath to Giants Grave, near Briton Ferry
History: On 12 July 1790 a meeting was held at the Ship & Castle at Neath, attended by Lord Vernon and local people, at which it was resolved that a canal from Pontneddfechan to Neath would be of great public benefit. On 13 September 1790 a meeting held to approve the line of the canal, surveyed by Thomas Dadford Junior, his father and brother John. Promoted by an Act of 1791. By Mid 1792 Thomas Dadford Junior found it necessary to leave his post of General Surveyor, due to his being given the contract to build the Monmouthshire Canal.Thomas Sheasby replaced him. Ynysbwllog Aqueduct opened in 1792. The canal is now carried in pipes across the remains of this aqueduct. The canal was completed in 1795, but in May 1798 an Act of Parliament passed to extend the canal by 2.5 miles to near Briton Ferry. On 29 July 1799 the canal, extended to the Giant's Grave was opened. From 1882 to 1886 dividends were not paid. Navigation ceased on the Neath Canal in 1934 and about the same time the Tennant canal stopped carrying commercial traffic.
See Priestley's Navigable Rivers and Canals for more information.
1790 | On 12 July 1790 a meeting was held at the Ship & Castle at Neath, attended by Lord Vernon and local people, at which it was resolved that a canal from Pontneddfechan to Neath would be of great public benefit. | |
1790 | On 13 September 1790 a meeting held to approve the line of the canal, surveyed by Thomas Dadford Junior, his father and brother John. | |
Summer 1790 | Assisted his father and brother (both called Thomas) in making a survey of the line of the proposed canal. | |
July 1790 | He was asked to make a survey of the proposed route of the canal, which he did with his father and brother John. | |
September 1790 | His estimate of £25,716 for the canal was approved. | |
1791 | Promoted by an Act. | |
1791 | He became a shareholder in the new company. | |
1791 | As engineer-contractor he assisted Thomas Dadford, the General Surveyor of the canal. | |
Autumn 1791 | Appointed General Surveyor to superintend occasionally the Works' at a daily salary. | |
1792 | By Mid 1792 Thomas Dadford Junior found it necessary to leave his post of General Surveyor, due to his being given the contract to build the Monmouthshire Canal.Thomas Sheasby replaced him. | |
1792 | Ynysbwllog Aqueduct Opened. The canal is now carried in pipes across the remains of this aqueduct. | |
1792 | Did a survey for a proposed canal and tramroad link to the Glamorganshire Canal. | |
Mid 1792 | He was employed as engineer-contractor and undertook to build the rest of the canal, from (and including) the Ynsbwllog Aqueduct to Glynneath by 1st November 1793 for £14,886, of which £2,800 was to be retained at interest for three years after the completion of the canal against any work found to need rectifing. | |
1795 | Completed in 1795, but in May 1798 an Act of Parliament passed to extend the canal by 2 1/2 miles to near Briton Ferry. | |
September 1797 | Surveyed the line for an extension of the canal to Giant's Grave near Briton Ferry. | |
1798 | In May 1798 an Act of Parliament passed to extend the canal by 2 1/2 miles to near Briton Ferry. | |
May 1798 | He was engineer for the construction of the 2½ mile extension of the canal from near Melincrythan pill to Giant's Grave near Briton Ferry. | |
1799 | On 29 July 1799 the canal, extended to the Giant's Grave was opened. | |
1800 | Surveyed the line for a tramroad on behalf of the company. | |
May 1802 | Surveyed the line for a tramroad with James Birch. | |
Early 1803 | He was engineer for the 8 mile tramroad from the canal head at Pont Walby to Aber-nant. It was finished within two years. | |
1836 | He wrote to Charles Tennant "I understand they are now talking in earnest about extending the Neath Canal to Aberavon". He had made a plan and survey for a similar extension to Port Talbot many years before. | |
1882 | From 1882 to 1886 dividends were not paid. | |
1886 | From 1882 to 1886 dividends were not paid. | |