![]() Text and photographs copyright of Jim Shead. |
|
Description: Was a 5 mile 7 furlong, 25 locks, broad canal from Terras Pill, Looe, Cornwall, to Moorswater near Liskeard used to carry lime and sea-sand.
History: Authorised by an Act of 1825, fully open in 1828, closed around 1910.
See Priestley's Navigable Rivers and Canals for more information.
Liskeard & Looe Union Canal
1777 | He was consulted on the possibility of a canal and proposed a canal from Sandplace, 2miles above East Looe, to Bank Mill bridge, 2.5 miles from Liskeard. He estimated it would cost £17,495 for a 15-mile canal with two inclined planes. | |
1823 | He was called in to advise on the making of a canal, railway and turnpike road, all of which he said were possible. On the question of a canal he ruled against locks and recommended a tub-boat canal with inclined planes at an estimated cost of £14,000. | |
1823 | He re-surveyed the proposed route with John Edgcumbe and Thomas Esterbrooke. | |
Late 1823 | Resurveyed the line of the canal with Robert Coad and Thomas Esterbrook, estimating the cost at £12,578. | |
Late 1823 | Resurveyed the line of the canal with Robert Coad and John Edgcumbe, estimating the cost at £12,578. | |
Early September 1823 | He asked to prepare a report to support the planned Bill for the authorisation of the canal. | |
1825 | Authorised by an Act. | |
1825 | Was engineer for the canal. | |
1828 | Fully open. | |
1858 | He was engineer for the railway line that the canal company were builing alongside the navigation. | |
1910 | Closed around 1910. | |
Description: Original title of the canal from Leicester to Market Harborough, now part of the G.U. Leicestershire Section.
History: Authorised by an Act of 1793, in 1797 was completed to Debdale wharf about 6 miles from Market Harborough, a new Act was obtained in 1805 and the canal reached Market Harborough in 1809. Purchased in 1894 by the Grand Junction.
See Priestley's Navigable Rivers and Canals for more information.
Early 1792 | He was asked to do a survey to extend the navigation from Leicester to Market Harborough. | |
Late 1792 | He did the survey for the canal and recommended a line to join the Grand Junction Canal at Gayton, with a branch to the Nene at Northhampton if the cost were reasonable. He did the final plans for the Bill together with Christopher Staveley. | |
June 1792 | He commented on the extension of the line from Market Harborough to Northampton and was later appointed engineer. | |
1793 | Authorised by an Act. | |
1793 | He worked with John Varley on the parliamentary survey for the canal under William Jessops direction. He was also joint engineer with Varley at the start of work on the canal but did not stay long. | |
1793 | He and Christopher Staveley both started work as engineers at the Leicester end of the canal. | |
24 October 1794 | The canal was open to Blaby and the committee "Ordered that Mr Varley the Engineer do contract for a Boat load of good coal to be conveyed as far as it will pass on the Union line on Monday to be sold for the benifit of the company". | |
July 1796 | It was suggested that Saddington Tunnel was out of straight. He offered to pay the costs if it was and entered into a £2,000 bond. The problem was not found to be very serious. | |
July 1796 | In his role as assistant engineer of the canal he discovered that Saddington Tunnel was not straight. | |
1797 | Completed to Debdale wharf about 6 miles from Market Harborough. | |
1802 | He was called in to report on James Barnes' proposals for a line to connect to the Grand Junction Canal. He agreed with the start and finish points but proposed a longer course to the east with less lockage. This was to go through Market Harborough, the upper Welland valley, Maidwell, Cottesbrooke, Hollowell, Ravensthorpe and Hodenby, with a branch to Rushton at a total cost of £228,207. | |
1805 | A new Act was obtained. | |
After 1805 | He was appointed to build the line to Market Harborough. | |
1808 | He and James Barnes were employed to do another survey for a connection to the Grand Junction Canal. | |
1809 | The canal reached Market Harborough. | |
13 October 1809 | His construction of the line to Market harborough was completed at the cost of £40,500 for the basin, buildings and 6¾ miles of canal. | |
1894 | Purchased by the Grand Junction. | |
Description: A plan for a canal from Lechlade to Abingdon to by-pass the navigational difficulties of the upper Thames.
History: Proposed in 1783, surveyed in 1784 never authorised or built.
1784 | He survyed a 22¾ mile line from Kempsford on the Thames & Severn Canal to Abingdon to by-pass 45¾ miles of difficult river navigation. |
Description: This 42 mile canal runs from Tewitfield to Preston and was from its openning detached from the main canal system although it had a connecting tram-way link from 1803 until 1860s. The opening of the Ribble Link in 2002 finally gave it a waterway connection to the main system.
History: Promoted by Acts of 1792, 1793, 1796, 1800, 1807 and 1819. Two miles of canal have been closed at Preston and the waterway above Tewitfield was closed by the Transport Act of 1955.
See Priestley's Navigable Rivers and Canals for more information.
November 1771 | He was approached to do the survey for the canal but it was carried out by Robert Whitworth. | |
1772 | He did a survey and put foward a plan for a line from the Leeds & Liverpool at near Eccleston crossing the Ribble below Penwortham Bridge then west towards Kirkham before turning north then east to Barton. The canl then continued north to Lancaster where it crossed the Lune just below Skerton Bridge.The long 54½ mile pound ended with a rise of 86 feet at Tewitfield before another level pound covered the last 18 miles to Kendal. The committee asked him to find an easier crossing of the Lune and he proposed a higher line locking up 24 feet from the Ribble, a shorter looptowards Kirkham but an additional loop up the Lune to Halton where a shorter aqueduct was needed. This reduced the rise at Tewitfield to 62 feet and the whole rise was around ½ mile longer. | |
1787 | He proposes to build a cut from the River Winster, near where it joined the the River Kent estuary at Castle Head (SD422799), northeast across Foulshaw Moss to Nether Levens where it would join the River Kent. The Kent was then to be diverted south-southwest along the coast to Arnside where it would turn south along the coastline to the deep water at Heysham Head. The scheme was intended to provide drainage as well as navigation. | |
8 June 1791 | Was asked to re-survey Whitworth's line, together with Robert Dickinson and Richard Beck, and to extend it southward to Worsley. | |
8 June 1791 | Was asked to re-survey Whitworth's line, together with Robert Dickinson and John Longbotham, and to extend it southward to Worsley. | |
8 June 1791 | Was asked to re-survey Whitworth's line, together with Rihard Beck and John Longbotham, and to extend it southward to Worsley. | |
October 1791 | He was asked to resurvey Robert Whitworth's line and extend it southward to Worsley. | |
1792 | Promoted by Act. | |
January 1792 | He did a survey in December and January and recommended a broad canal from Westhoughton, in the coalfield between Bolton and Wigan, running north on a 15½ mile level to Clayton Green. Here it would descend 222 feet in 32 locks to the embankment and aqueduct over the river to Preston to join Whitworth's line. | |
July 1792 | He is appointed engineer to reside five months a year at Lancaster and to attend at other times as requested for a salary of £600 a year. | |
July 1792 | Appointed assistant surveyor. | |
1793 | Promoted by Act. | |
1793 | He is appointed resident engineer and superintendent. | |
January 1793 | His plans for the Glasson branch were approved. | |
1794 | Was appointed resident engineer for the canal south of the Ribble and was assisted by Thomas Fletcher. | |
1794 | Was appointed assistant to Henry Eastburn, the resident engineer south of the Ribble. | |
January 1794 | Appointed assistant resident engineer with special responsibilities for the Lune Aqueduct foundations. | |
January 1794 | He started pile driving for the Lune Aqueduct foundations inside 20-foot coffer dams kept dry by steam pumping. | |
1795 | He was called in to arbitrate in the disputes between Archibald Millar the resident engineer and the contractors John Pinkerton and John Murray. | |
1795 | He had many complaints about the bad work of the contractors, John Pinkerton and John Murray, and their inattention to his instructions. Robert Whitworth was called in to arbitrate and the work was taken back and let out again as smaller contracts under Millar's supervision. | |
6 October 1795 | The canal committee record the presentation of a silver cup to him "as a reward for his extra care and attention in superintending the Foundations of the Lune Aqueduct". | |
1796 | Promoted by Act. | |
1797 | Lune Aqueduct opened, 62 feet above the River Lune, built by Rennie. | |
1799 | He advises the canal committee to build a 5-mile tramroad from the South End at Clayton Green to Preston and to make a short extension to the North End of the canal from Spital Moss, thus connecting the two portions of the canasl across the Ribble. | |
1799 | His contract was not renewed. | |
July 1799 | As resident engineer for the whole canal he reported that the canal was now open for 12 miles to Johnson's Hillock and almost ready to Clayton Green except for Whittle Hills Tunnel. | |
July 1799 | His contract was not renewed and by this date he was no longer a resident engineer on the canal. | |
1800 | Promoted by Act. | |
Mid 1801 | Submitted a design for an aqueduct with three 120 foot spans as an alterative to a tramroad crossing of the Ribble. | |
May 1801 | He and John Rennie reported on the schemes for crossing the Ribble and recommeded a 640-feet long aqueduct 57 feet high with three 116-feet elliptical arches. | |
May 1801 | He and William Jessop reported on the schemes for crossing the Ribble and recommeded a 640-feet long aqueduct 57 feet high with three 116-feet elliptical arches. | |
May 1801 | Around this date he produced a drawing for an aqueduct across the River Ribble with pointed arches, three of which spanned the river. | |
6 July 1801 | The committee record that Rennie and Jessop have approved his plans for a tramroad as a temporary crossing of the Ribble valley. | |
1805 | He made two surveys for the continuation of the canal to Kendal, one through Hincaster with a 340-yard tunnel and the other a more direct route with a 670-yard tunnel at Rains Hall at the cost of £71,755 for the cheaper option. He also suggested a 13-mile tramroad with three inclined planes at a cost of £38,575. | |
July 1806 | Pumping of water from the Ribble started after he finished the tunnel between the canal and the river and other works. He had been assistant engineer for some years after 1794. | |
1807 | Promoted by Act. | |
1812 | Was appointed resident engineer and prepared detailed estimates for the Kendal extension, which he costed at £98,095. | |
1813 | He advised on two proposed schemes for crossing the Ribble. The first for a level crossing he considered impracticable. The second for a lower level aqueduct with increased lockage on both sides he estimated at £160,537 and thought that it would endanger water supplies. | |
May 1817 | Appointed as engineer responsible for for completing works north of Tewitfield Locks. | |
1819 | Promoted by Act. | |
1819 | Left the canal company. | |
1820 | He is appointed superintendent for the whole canal. | |
June 1826 | After completing the Glasson Dock branch he resigns to become engineer to the Macclesfield Canal. | |
June 1826 | He took over the role of engineer following the departure of William Crossley. | |
Autumn 1830 | He was asked to report on the conversion of the company's tramroad into a railway.He recommended retaining the exsisting engine-worked incline from the Ribble bridge, the building of four self-acting inclines and two diversions at a total cost of £11,895. | |
1831 | He makes four positive suggestions to deal with the treats posed by the proposed Wigan & Preston Railway. 1 - Convert the tramroad into a railway, to speed up transhipment. 2 - The same but in addition to make suitable changes to permit locomotive working. 3 - Seek amalgamation with the railway and abolish the tramroad. 4 - Abolish the tramroad so forcing the railway to make branches to the pits. | |
1844 | In recognition of his work in negotiating with railway companies his salary was fixed as a minimum of £1,000 a year for the rest of his time with the company. | |
October 1846 | On the death of his father, Samual aged 83, he succeeded to the role of clerk. | |
1849 | He acted as arbitrator in a dispute between the company and the Lancaster & Carlisle Railway awarding £55,552 of outstanding tolls to the canal company. | |
3 December 1872 | He died still with the company after 60 years service. | |
1955 | The waterway above Tewitfield was closed by the Transport Act of 1955. | |
Description: A tributary of the Great Ouse, originally navigable for 24.5 miles from Bury St Edmunds but now only navigable from Judes Ferry, 10 miles.
History: Promoted by Acts of 1700 and 1817
See Priestley's Navigable Rivers and Canals for more information.
1700 | Promoted by Act. | |
1817 | Promoted by Act. | |
Description: Runs from Evesham (where it joins the Upper Avon Navigation) to Tewkesbury where in joins the Severn.
History: Was in the hands of the Perrotts of Craycombe, Fladbury until 1924 when William Fisher took over and formed the Lower Avon Navigation Company. Later it was transferred to John Whitehouse of Evesham, then , in 1949, to C D Barwell. On 1 August 1950 the Lower Avon Navigation Trust Ltd was formed to restore the river. Avon Lock at Tewksbury had two new gates fitted in 1952 and repairs were done to the lock chamber. In 1953 Chadbury lock rebuilt by the Royal Engineers. The following year Wyre lock, weirs and sluice gates extensively repaired and restored and in 1955 work started on deepening Pershore Lock, which was deepened by three feet, new gates fitted and the navigation arches of the old bridge deepened by 1956. Fladbury Lock was deepened by three feet in 1958 and in 1961 Cropthorne/Fladbury water gate was removed and the channel deepened. The whole navigation, from Evesham to Tewksbury, was formally reopened on 10 June 1962.
1924 | Was in the hands of the Perrotts of Craycombe, Fladbury until 1924 when William Fisher took over and formed the Lower Avon Navigation Company. | |
1949 | It was transferred from John Whitehouse of Evesham, to C D Barwell. | |
1950 | On 1 August the Lower Avon Navigation Trust Ltd was formed to restore the river. | |
1952 | Avon Lock at Tewksbury had two new gates fitted and repairs were done to the lock chamber.. | |
1953 | Chadbury lock rebuilt by the Royal Engineers. | |
1954 | Wyre lock, weirs and sluice gates extensively repaired and restored. | |
1955 | Work started on deepening Pershore Lock. | |
1956 | Pershore Lock deepened by three feet, new gates fitted and the navigation arches of the old bridge deepened. | |
1958 | Fladbury Lock deepened by three feet. | |
1961 | Cropthorne/Fladbury water gate removed and channel deepened. | |
1962 | From Evesham to Tewksbury formally reopened on 10 June. | |
1997 | Gongoozlers at the Gate by Kathleen Balchin, Published by Silverswan 1997 The author and her husband spent three years in the 1980s as lock keepers at Tewkesbury on the Lower Avon. This is an account of their time there. | |
Description: Various plans for a canal link from the Stratford Canal to the Regents Canal. The 1836 route being 113 miles long. Never authorised or built.
History: Started to be considered in 1827 and the last known dicussions of the plan was in 1838.
12 November 1827 | An article appeared in the Aris's Birmingham Gazette in which he is named as engineer for this canal from the Stratford-upon-Avon Canal, pssing under the Oxford Canal, to join the Grand Junction Canal at at Braunston with a branch to the Coventry Canal. This route had only 20 locks compared with 54 via Fazeley and 77 through Warwick. | |
After February 1830 | He withdrew from the scheme after the Bill was rejected due to serious irregularities in the subscribers list presented to parliament. | |
Late 1833 | He surveyed the line of the canal. | |
March 1838 | A meeting was held in his office to discuss the project. No later discussions of this canal are known. |
Description: A 15.75 mile canal with 10 locks between the Loughbourgh Navigation and Leicester. Now part of the Grand Union Leicester Section.
History: Authorised by an Act of 1791 and fully open in 1794. The 8.75 mile canal and tramroad Charnwood Forest branch was disused by 1799 and abandoned in 1848. The main line became part of the new Grand Union Canal Company in 1932.
See Priestley's Navigable Rivers and Canals for more information.
12 July 1790 | He was asked to make a survey for the line of the proposed canal. | |
Autumn 1790 | He and Christopher Staveley proposed a canal and river line to Leicester, the canalisation of the Wreak to Melton Mowbray and a rail and water line to the Leicestershire collieries. | |
Autumn 1790 | He reported with William Jessop proposing a canal and river line to Leicester. | |
Autumn 1790 | He and William Jessop proposed a canal and river line to Leicester, the canalisation of the Wreak to Melton Mowbray and a rail and water line to the Leicestershire collieries. | |
May 1791 | He was appointed engineer at £300 a year. | |
May 1791 | He was appointed surveyor at £200 a year. | |
1795 | He was appointed engineer of the completed navigation. | |
Summer 1796 | He was called in to judge if Saddington tunnel was straight. He said it was not and James Barnes later confirmed his view. | |
February 1799 | The reservoir on the Forrest line of the canal burst and he estimated the cost at £6,193 for repairs and compensation. | |
Late 1801 | About this date he was called in to see if the Loughborough to Nanpantan rail link could be replaced by a canal. | |
1825 | He was appointed joint engineer with his father. | |
1827 | He became engineer and superintendent following his father's death. | |
1830 | Around this time he was called in to advise on the problem of reopenning the Forest line. A horse railway throughout the line at the cost of £44,585 was agreed but rejected by shareholders. | |
1833 | Called on his solicitor to announce that he owed the company £1,400. He then disappeared leaving his records inaccessible. The records were recovered but Staveley and the money were not seen again. | |
Early 1833 | He and Thomas Hill were consulted on the horse railway the company proposed to build along a similar route to the Forest line. | |
Early 1833 | He and John Rastrick were consulted on the horse railway the company proposed to build along a similar route to the Forest line. | |
1846 | He proposed to the company that they, together with the Loughborough company and himself, should jointly build a railway line from Derby to Rugby along the Soar valley. |